QS 21-8 Tercer reports
2. Explain how standard costs help managers apply this concept to monitor and control costs Tercer reports the following on one of its products. Compute the direct materials price and quantity variun.as ces Direct materials standard ( lbs.$2/lb.) Actual direct materials used Actual finished units produced , . … Actual cost of direct materials used. $8 per finished unit 300,000 Ibs 60.000 urits $535,000